%3
International Construction Contracts: An Analysis Of Their Nature, Con

International Construction Contracts: An Analysis Of Their Nature, Content And Disputes With Resolution Mechanisms, Particularly From Swiss And Turkish Legal Perspective


Basım Tarihi
2023-11
Sayfa Sayısı
133
Kapak Türü
Karton
Kağıt Türü
1.Hamur
Basım Yeri
Ankara
Stok Kodu
9786052646106
Boyut
16x24
Baskı
1



260,00 TL 252,20 TL
(Bu ürünü aldığınızda 212 puan kazanacaksınız)
   212

Mehmet Ali DEMİRCİ

 

TABLE OF CONTENTS

FOREWORD.7

ÖZET .9

ABSTRACT .11

TABLE OF CONTENTS 13

ABBREVIATIONS19

CHAPTER ONE

THE NATURE OF CONSTRUCTION CONTRACTS

Exclusive Structure of Construction Projects23

Particularities of Construction Contracts .24

2.1. Custom-Made Projects.24

2.2. Duration .25

2.3. Complexity .26

2.4. Construction Site27

2.5. Financial Dimension .27

2.6. International Scope29

2.7. Voluminous Documentation 30

2.7.1. Plant Description/Specification .31

2.7.2. Design 31

2.7.3. Bill of Quantities (BoQ) 32

2.7.4. Contract Price 34

2.7.5. Payment Schedule / Milestones 34

 

14 Table of Contents

2.7.6. Others . 35

2.8. Need for Flexibility and Reformation. 35

Parties of a Construction Project 36

3.1. Employer (Owner-Client-Customer)  36

3.2. Contractor(Entrepreneur) 37

3.3. Subcontractor(s)  38

3.4. Engineer / Architect. 39

3.5. Quantity Surveyor (Cost Consultant/Engineer) . 40

3.6. Others 40

Obligations of Parties . 41

4.1. Contractor’s Obligations 41

4.1.1. Execution of the Work  41

4.1.2. Duty to Inform. 42

4.1.3. Delivery of the Work . 43

4.1.4. Statutory Obligations  44

4.2. Employer’s Obligations 44

4.2.1. Payment of the Contract Price  44

4.2.1.1. Fixed Price / Lump Sum: . 44

4.2.1.2. Unit Price / Re-Measurement: 45

4.2.1.3. Cost-Reimbursement / Cost-Plus:. 46

4.2.2. Non-Hindrance and Collaboration  46

4.2.3. Duty of Notice for Defects. 47

Types of Construction Contracts . 48

5.1. Build-Only or Design-Bid-Build  48

5.2. Turn-Key or Design and Build (DB). 49

5.3. Engineering, Procurement, and Construction (EPC)  50

 

Table of Contents 15

5.4. Build, Operate, and Transfer (BOT) 51

5.5. Construction Management (CM) .51

Place in Swiss and Turkish Legal System 52

The Integral Part of Construction Contracts: Standard Rules57

7.1. FIDIC .58

7.1.1. FIDIC Red Book 60

7.1.2. FIDIC Yellow Book61

7.1.3. FIDIC Silver Book62

7.2. NEC.62

7.3. JCT 63

 

CHAPTER TWO

 

POTENTIAL DISPUTES AND FORCE MAJEURE & HARDSHIP

 

Variations / Changes .65

1.1. Possible Variation Cases.65

1.2. The Scope of Variations66

1.3. The Role of Engineer in Variations .68

1.4. Valuation Matter69

Defects70

2.1. Before Taking Over.71

2.2. After Taking Over .72

2.2.1. Defects Notification Period (DNP) .72

2.2.2. Remedies Against Defects .73

2.3. Serial Defects .74

2.4. Performance Certificate .74

 

16 Table of Contents

Delays 75

3.1. Types of Delays 78

3.1.1. Critical / Non-Critical Delays . 78

3.1.2. Excusable / Non-Excusable Delays  79

3.1.2.1. Compensable / Non-Compensable Delays:. 80

3.1.3. Concurrent Delays. 80

3.2. The Completion Date. 83

3.3. Extension of Time (EoT) . 84

3.4. Entitlement to Additional Expenses and Loss 86

3.5. Liquidated Damages (LDs) . 87

Force Majeure 89

4.1. Differences Arising From Impossibility Types  92

4.2. Perspective of FIDIC. 93

4.2.1. Consequences of Exceptional Events  95

Hardship. 96

Force Majeure and Hardship Scenarios With Current Issues Through The

Example of A NPP Project in Turkey 98

6.1. COVID-19 . 99

6.2. Climate Chance 100

6.3. Sanctions and Embargos 103

6.4. Inflation or Fluctuations  104

Termination 105

7.1. Employer’s Termination  106

7.2. Contractor’s Termination and Suspension  108

 

Table of Contents 17

 

CHAPTER THREE

 

DISPUTES RESOLUTION METHODS AND MULTI-TIER CLAUSES

 

Conciliation and Mediation .110

Dispute Boards112

2.1. FIDIC DAAB.113

Arbitration 114

3.1. Features and Advantages.115

3.2. Drawbacks116

3.3. Ad Hoc vs Institutional Arbitration.118

Multi-Tier Clauses 119

 

CONCLUSION.123

BIBLIOGRAPHY 127

Yorum yaz
Bu kitaba henüz yorum yapılmamış.
Bonus Card ( Garanti - Teb - Denizbank - Şekerbank vb. )
Taksit Sayısı
Taksit tutarı
Genel Toplam
1
252,20   
252,20   
Cardfinans ( Finansbank )
Taksit Sayısı
Taksit tutarı
Genel Toplam
1
252,20   
252,20   
Maximum Card ( İş Bankası - Ziraat Bankası )
Taksit Sayısı
Taksit tutarı
Genel Toplam
1
252,20   
252,20   
Worldcard ( YKB - Vakıfbank - Anadolubank - Albaraka )
Taksit Sayısı
Taksit tutarı
Genel Toplam
1
252,20   
252,20   
Diğer Kartlar
Taksit Sayısı
Taksit tutarı
Genel Toplam
1
252,20   
252,20   
Kapat